Transmission & Distribution
  • AP TRANSCO :-

    220/132kV, 100MVA, Kuppam S/S, along with associated transmission lines (220kV D/C - 65kms) was commissioned by Aster on 30-Mar-2017. Additionally one no: 220kV bay at Palamaneru S/S in Chittor Dist. Was also commissioned on 25-Mar-17. These works were awarded to Aster by AP Transco.

  • POWERGRID :-

    With the charging of W-3 circuit of 765kV, D/C, Hexazebra Raipur Wardha Transmission line, Aster has completed execution work of the said line on 29-Mar-17. Total load flow on the circuit was 800 MW. Earlier circuit W-4 of the said line was charged on 24-Mar-2017 and load flow on this circuit was 1100 MW.
    Award for the said line was placed on Aster by POWERGRID.

  • Aster has been selected as a consultant by APSFL for preparing DPR on development of communication tower infrastructure in the state of Andhra Pradesh.

  • "Aster is executing 4nos. 220/33KV SAS substations and associated transmission lines for evacuation of 1000MW of Solar Power from Gani Solar Power Park in Dist: Kurnool AP for AP Transco".

  • "765 kV Raipur-Wardha Transmission line nearing completion".
 
  • "Stringing work in progress in 400kv Suratgarh - Babai Transmission line of RRVPNL".

 